1 – 4 of 4Jemima Antwiwaa Ottou, Bernard Kofi Baiden, Gabriel Nani and Martin Morgan Tuuli
This research investigates the implementation of Six Sigma in competitive tendering processes to address persistent delays by identifying the potential benefits and challenges of…
Abstract
Purpose
This research investigates the implementation of Six Sigma in competitive tendering processes to address persistent delays by identifying the potential benefits and challenges of implementing Six Sigma in construction competitive tendering processes. The results seek to encourage practitioners to implement Six Sigma in addressing competitive tendering process delays.
Design/methodology/approach
Literature was reviewed to identify the benefits and challenges of Six Sigma implementation in construction processes and categorized under broad headings. Three case studies were used to authenticate the literature findings by applying Define-Measure-Analyse-Improve-Control to their construction competitive tendering processes. Furthermore, quality tools and techniques together with documentary analysis, content analysis and determination of frequencies of quantitised qualitative data were employed to identify potential benefits and challenges.
Findings
The most common Six Sigma benefits achievable in construction competitive tendering are Time Related benefits. Other benefits likely to emanate as ripple effects are Customer Focus Related, Quality Related, Process Improvement Related, Human Resource Related, Finance Related and Decision Related. However, implementation challenges should be expected.
Practical implications
Six Sigma implementation in construction competitive tendering promotes time efficiency. It is expected that this will encourage quantity surveyors, procurement practitioners and their institutions to implement Six Sigma in addressing persistent delays in their competitive tendering processes.
Originality/value
This paper demonstrates the use of merged approach under mixed method to identify the benefits and challenges of Six Sigma implementation in construction competitive tendering process within the Ghanaian context.
Details
Keywords
Ebenezer Adaku, Victor Osei-Poku, Jemima Antwiwaa Ottou and Adwoa Yirenkyi-Fianko
The phenomenon of delayed payment to contractors, particularly in the construction industry, is a vital one and has implications for the health of economies of both developing and…
Abstract
Purpose
The phenomenon of delayed payment to contractors, particularly in the construction industry, is a vital one and has implications for the health of economies of both developing and developed countries. However, the knowledge of this phenomenon seems patchy and scattered. This paper aims to provide a comprehensive overview of the knowledge on the subject matter with directions for future research.
Design/methodology/approach
A systematic literature review coupled with a scientometric analysis was used to identify the main strands of delayed payment to contractor research as a basis for qualitative analysis and directions for future investigations.
Findings
Current trends of delayed payment to contractor research are categorised into five broad themes, namely: causes, effects, mitigation measures, ethical and law and regulatory issues. On the basis of these themes, directions for future research are proffered.
Originality/value
To the best of the authors knowledge, this is the first attempt at providing a comprehensive and an integrated knowledge on delayed payment to contractor research with pointers for further investigation and policy directions.
Details
Keywords
Adwoa Boadua Yirenkyi-Fianko, Ernest Kwesi Yanful and Jemima Antwiwaa Ottou
Total organic carbon (TOC), dissolved organic carbon (DOC) and other physicochemical parameters of the Birim River, which serves for drinking and domestic purposes for rural…
Abstract
Purpose
Total organic carbon (TOC), dissolved organic carbon (DOC) and other physicochemical parameters of the Birim River, which serves for drinking and domestic purposes for rural mining communities, were analysed to assess the suitability of water quality for human consumption.
Design/methodology/approach
In total, 40 samples were collected from 20 sampling sites during the rainy season from July to September and the dry season from December to February in addition to two repeat samples and two blank samples. Samples were analysed for physiochemical parameters and the results were compared with World Health Organisation standards (WHO).
Findings
Data obtained for both rainy and dry seasons indicated TOC ranged from 1.1 to 7.3 mg/L and DOC 1–7.2 mg/L; pH, 5.6–8.63; temperature, 23.3–29.3°C; turbidity, <1.00–869NTU; apparent colour, <2.5–600 mg/L Pt-Co; true colour <2.5–150 mg/L Pt-Co; alkalinity, 27.8–80.4 mg/L; total suspended solids, <1.00–998 mg/L; electrical conductivity, 82–184 µS/cm; and bicarbonate, 33.9–98.1 mg/L. Particulate organic carbon (POC) was constituted between 1 and 10% of the TOC. Values for pH, turbidity, total suspended solids, and true colour indicated contamination of the river. p -value of <0.05 between seasons for the physicochemical parameters also suggests that the water is polluted.
Practical implications
Water from the Birim River is unsuitable for human consumption and may constitute a serious health risk to the consumers.
Originality/value
The paper yields immense value to inhabitant of communities using surface water affected by mining activities, policy makers in sustainability. It warns of the unsuitability of water from the Birim River for human consumption due to the potential health risk to consumers.
Details
Keywords
Jemima Antwiwaa Ottou, Bernard Kofi Baiden and Gabriel Nani
Project management tools and techniques have been widely adopted in the construction industry; however, its combination with Six Sigma and application in construction procurement…
Abstract
Purpose
Project management tools and techniques have been widely adopted in the construction industry; however, its combination with Six Sigma and application in construction procurement has not been widely researched. This paper explores the use of Six Sigma Project Procurement (SSPP) and its potential applications in public sector construction procurement.
Design/methodology/approach
The role of Six Sigma and project management in construction is critically evaluated using three case studies to demonstrate their application in public procurement.
Findings
The use of SSPP by public sector organisations creates efficient and effective construction procurement processes by addressing delays. The proposed timelines for competitive tendering in the Ghanaian Public Procurement Manual are not realistic.
Research limitations/implications
This paper contributes to and broadens the limited body of evidence and knowledge of applying SSPP to public procurement processes and identifies areas for further research.
Practical implications
Project management will continue to expand in the global construction industry. However, what will eventually determine if SSPP is embraced by public sector construction depends on the leadership and success of its execution. The application of SSPP to public construction procurement will address delays and lead to significant time reduction of the process. This will eliminate the major issue (delay) accounting for deficiencies in the process.
Originality/value
The paper yields immense value to construction project management researchers and practitioners, especially in the public sector. It recommends the inclusion of Six Sigma to promote focus on actual instead of perceived problems and advocates for decisions-making based on facts which will ensure continuous improvement.